History

The history of the Snowy River Project dates back to 1905 when the main “Birthday Reef” was discovered by a small prospecting group. Mining is said to have commenced shortly afterwards in 1906 and the operation continued for 45 years up until 1951.

During this period the mine produced about 733,000 ounces of 21 tonnes of gold. It was worked from two shafts – the Blackwater Shaft and Prohibition Shaft – and mined to a depth of 800 metres across 16 levels.

The mine was still operating in profitable ore when the collapse of the Blackwater Shaft resulted in the closure of the operation. It is still considered one of the richest and most consistent gold reefs discovered anywhere in the world.

Key Metrics

244 koz @ 6.03 g/t

Ore Reserves

795 koz @ 23.1 g/t

Mineral Resources

~60 koz @

Annual Production over LOM

~A$2,400/oz

All-in Cost over Life of Mine

10+ year

Mine Life

96%

Total Recovery

Gold mineralisation at Blackwater is hosted in narrow quartz veins. Most of the gold-bearing quartz veins in the Reefton Goldfield are arranged along a linear belt that runs north-south through the Greenland Group sequence. This suggests the presence of a deep-seated structure that has tapped a large reservoir of mineralised fluid. All the gold production from the Blackwater Mine came from the Birthday Reef, a single quartz vein that was mined continuously for over 1,000m in strike and over 710m in depth.

Snowy River JORC 2012 Mineral Resources and Ore Reserves Estimate (MROR) incorporates drilling up to March 2025 and includes information from 144 completed diamond drill holes (25,774m) drilled by Endura from February 2023 to March 2025.

Probable Ore Reserves

DepositTonnes (kt)Grade (g/t Au)Contained Gold (koz)
Christmas and Birthday Reefs1,2356.03240
Stockpile215.964
Total Probable Ore Reserves1,2566.03244

Mineral Resource Estimate

JORC (2012)
Resource ClassificationTonnes

(kt)
Grade

(g/t Au)
Contained Gold

(koz)
Panel A
(-270 to -600mRL)
Indicated36222.7264
Inferred10025.281
Total Indicated
and Inferred
46223.2345
Panel B
(-600 to -1030mRL)
Inferred61023.0450
Global Mineral
Resource Estimate
Indicated36222.7264
Inferred71023.3531
Total Indicated
and Inferred
1,07223.1795

Key Milestones

Acquisition of Snowy River
Completion of feasibility study
SEPT 2025
Construction commenced
Q2 - 2027
Commercial production
Regulatory and environmental approvals
Project funding
Q4 - 2026
First Gold